What should the program manager do next?

A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?A . Request permission from the program governance board to initiate program closure activities.B . Present additional opportunities to the program sponsor.C . Apply...

June 30, 2021 No Comments READ MORE +

What is the other name for critical delivery dates?

What is the other name for critical delivery dates?A . Substantial completion.B . Phases.C . Flags.D . Milestones.View AnswerAnswer: D

June 30, 2021 No Comments READ MORE +

Which one of the following is an output of the communications control process?

You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?A . Approved change requestsB . Communications management planC . Stakeholder analysis chartsD...

June 29, 2021 No Comments READ MORE +

During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS). During the meeting, the master scheduler indicates that the master program schedule should include which...

June 29, 2021 No Comments READ MORE +

What document should you provide to Hal?

Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?A . InvoiceB ....

June 29, 2021 No Comments READ MORE +

Where are negative risks recorded?

Where are negative risks recorded?A . Negative risk registerB . Risk management planC . Risk registerD . Issues logView AnswerAnswer: C

June 29, 2021 No Comments READ MORE +

What should the program manager do to ensure communications on the component projects are consistent?

The project manager of project A develops a communications management plan . The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff. What should the program manager do to ensure communications on the component projects are consistent?A . Request a...

June 28, 2021 No Comments READ MORE +

At what point in the project is the risk of failing to achieve the project objectives the greatest?

At what point in the project is the risk of failing to achieve the project objectives the greatest?A . During project planningB . During the project executionC . At the project startD . At the end of the projectView AnswerAnswer: C

June 28, 2021 No Comments READ MORE +

What two things must be documented if you wish to terminate a vendor's contract?

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?A ....

June 28, 2021 No Comments READ MORE +

What should the program manager do next?

A component project of a multiyear program delivers all expected products and services as anticipated . The component project manager obtains approvals from the stakeholders and transitions the benefits to operations. What should the program manager do next?A . Reassign the component project manager to another component project or activityB...

June 28, 2021 No Comments READ MORE +