Audit trail is established

Audit trail is establishedA . Only 1 is trueB . Only 2 is trueC . Both land 2are trueD . Neither 1 or 2 is trueView AnswerAnswer: A

January 1, 2021 No Comments READ MORE +

Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?

Which activity includes addressing the disadvantages of ‘doing nothing’ to those stakeholders that object to the programme?A . Analyse stakeholdersB . Sum ma rise risksC . Carry out a health checkD . Conduct a visioning workshopView AnswerAnswer: D

January 1, 2021 No Comments READ MORE +

Which is a purpose of a summary risk profile?

Which is a purpose of a summary risk profile?A . Explain the programme risk exposure in monetary termsB . Show the relationship between critical risks in a programmeC . Highlight any low probability benefits that are being managed as opportunity risksD . Determine the residual risk exposure, assuming that planned...

January 1, 2021 No Comments READ MORE +

Which describes an impact of a risk?

Which describes an impact of a risk?A . Effect on the programme if something goes wrongB . An event that might increase a programme's outcomeC . The amount of risk that will be toleratedD . Possibility that something will go wrongView AnswerAnswer: A

December 31, 2020 No Comments READ MORE +

Which is evidenced by the Business Case?

Which is evidenced by the Business Case?A . Continuing affordability of the programmeB . Responsibility for managing the Business Change TeamC . Information about what will be subject to reviewD . Risk responses for the initial programme risksView AnswerAnswer: A

December 31, 2020 No Comments READ MORE +

Which statement relates to preparing the programme plan?

Which statement relates to preparing the programme plan?A . Defining the approach to risk managementB . Describing deliverables to be produced in Defining a ProgrammeC . Appointing the Senior Responsible OwnerD . Processing large amounts of informationView AnswerAnswer: D

December 31, 2020 No Comments READ MORE +

Which is represented in a summary risk profile?

Which is represented in a summary risk profile?A . Category of risk responseB . Impact of an issueC . Likelihood of a riskD . Cause of a riskView AnswerAnswer: C

December 31, 2020 No Comments READ MORE +

Which statement relates to preparing the programme plan?

Which statement relates to preparing the programme plan?A . Defining the approach to risk managementB . Describing deliverables to be produced in Defining a ProgrammeC . Appointing the Senior Responsible OwnerD . Processing large amounts of informationView AnswerAnswer: D

December 31, 2020 No Comments READ MORE +

Which part of the scope of programme quality is MOST likely to be concerned with making best use of skills and experience?

Which part of the scope of programme quality is MOST likely to be concerned with making best use of skills and experience?A . Standards managementB . People managementC . Process managementD . Communications managementView AnswerAnswer: B

December 30, 2020 No Comments READ MORE +

What role description includes support for project assurance and health checks which is independent of the projects?

What role description includes support for project assurance and health checks which is independent of the projects?A . Programme ManagerB . Business Change ManagerC . Senior Responsible OwnerD . Programme OfficeView AnswerAnswer: D

December 30, 2020 No Comments READ MORE +