What do you need to consider?

You are upgrading a three-system landscape DEV – QAS – PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system .

What do you need to consider? Please choose the correct answer.
A . The upgrade of the PRD must be finished before you start new development in the DE
C . The transport domain of systems DEV and QAS must differ from the transport domain of system PR
E . The transport between Unicode and non-Unicode systems is forbidden.
F . The upgrade of the PRD must be finished before you import any transports from the upgraded DEV system into the PR

Answer: D

During the configuration of the DMO for SUM, how does the tool behave if option "Do not compare table contents" is selected regarding table comparison? Please choose the correct answer.

During the configuration of the DMO for SUM, how does the tool behave if option "Do not compare table contents" is selected regarding table comparison? Please choose the correct answer.
A . It performs a comparison on selected tables using check sum.
B . It performs a comparison on all tables using row counts.
C . It performs a comparison of all tables using check sum.
D . It does NOT perform any table comparison.

Answer: B

SUM was registered at the SAP Host Agent. Based on which information does the SAP Host Agent determine the path to the SUM directory.

SUM was registered at the SAP Host Agent. Based on which information does the SAP Host Agent determine the path to the SUM directory.
A . The path was stored in file host_profile during registration
B . The path was stored to the environment of user <sid>adm during registration
C . The path is taken from the URL entered in the browser to start SUM
D . The path was stored in file sumabap conf during registration

Answer: D

How does SUM recognize modification adjustment transports from predecessor systems? Please choose the correct answer.

How does SUM recognize modification adjustment transports from predecessor systems? Please choose the correct answer.
A . By searching for transport requests that are assigned to the project SAP_ADJUST
B . By searching for transport requests named <SID>K0<number>
C . By searching for transport requests in DIR_TRANS, subdirectory "transport"
D . By searching for transport requests in the file umodauto.Ist

Answer: D

Which circumstances will allow SUM to run without the creation of a shadow system? Please choose the correct answer.

Which circumstances will allow SUM to run without the creation of a shadow system? Please choose the correct answer.
A . Using the main configuration option "Single System" when installing an Add-On
B . Using the main configuration option "Single System" in case of an upgrade.
C . Using the database migration option (DMO) for SUM
D . Using the main configuration option "Standard" when applying SAP Support Packages

Answer: A

What is the different between the benchmaking and the repetition option of the Database Migration Option (DMO) of SUM?

What is the different between the benchmaking and the repetition option of the Database Migration Option (DMO) of SUM?
A . The benchmaking option allows you to migration a specified set of tables
B . The benchmaking option allows you to repeat the uptime migration
C . The repetition option allows you to run the migration without a shadow system
D . The repetition option allows you to repeat the complete migration

Answer: A

Which steps run before the beginning of the technical downtime, independent of your SUM configuration?

You want to perform an SAP S/4HANA conversion using SUM with DMO .

Which steps run before the beginning of the technical downtime, independent of your SUM configuration? There are 3 correct answers to this question.
A . Generation of the new ABAP loads in phase RUN_SGEN_GENER8
B . Import of upgrade and language data from the download directory in phase TABIM UPG
C . Activation of dictionary objects in phase ACT_UPG
D . Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE
E . Import of dictionary objects from the download directory in phase DDIC_UPG

Answer: B,C,E

What is the benefit of using the file UPGANA.XML from a previous SUM run? Please choose the correct answer.

What is the benefit of using the file UPGANA.XML from a previous SUM run? Please choose the correct answer.

A. To auto-fill specific fields on selected screens on the SUM UI

B. To make the progress information within SUM UI more accurate

C. To repeat specific phases during the SUM run

D. To skip selected phases during the SUM run

Answer: B