calculations?

An earned value-based project control system can use either of which two budgets as the basis of its calculations?A . Labor hours or dollars.B . Direct or indirect cost.C . Earned or budgeted cost yearly.D . Linear feet or dollars.View AnswerAnswer: A

May 15, 2025 No Comments READ MORE +

Which of the following is NOT required when initially planning a project?

Which of the following is NOT required when initially planning a project?A . Resource Identification and leveling.B . The duration of each task.C . A schedule that identifies tasks required on a project.D . Logical relationships between the tasks.View AnswerAnswer: A

May 13, 2025 No Comments READ MORE +

Which of the following will always describe the critical path? The path with

Which of the following will always describe the critical path? The path withA . The longest duration through the network.B . Zero float.C . Negative float.D . The shortest duration and negative float.View AnswerAnswer: B

May 7, 2025 No Comments READ MORE +

A driving relationship is _____________________.

A driving relationship is _____________________.A . A critical relationship.B . A finish-to-start relationship.C . The link between two related activities.D . The link between a predecessor and the activity whose dates it controls.View AnswerAnswer: D

May 6, 2025 No Comments READ MORE +

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?A . Use the progressed portion of the critical path of all the updates previous to the current update.B . Use...

April 29, 2025 No Comments READ MORE +

Which of the following is NOT a tool or technique used to perform scope planning?

Which of the following is NOT a tool or technique used to perform scope planning?A . Benefit cost analysis.B . Schedule performance indexing.C . Expert Judgment.D . Alternatives identification.View AnswerAnswer: B

April 29, 2025 No Comments READ MORE +

What is a key first step in developing a critical path method schedule?

What is a key first step in developing a critical path method schedule?A . Drawing a bar chart of the key phrases of the work.B . Defining the execution plan to meet the required scope of work.C . Setting out the resource to be used and its limitations.D . Drawing...

April 23, 2025 No Comments READ MORE +

At a minimum, periodic reporting must be done at what interval?

At a minimum, periodic reporting must be done at what interval?A . Monthly.B . As requested by the project manager.C . As requested by the owner.D . As specified in the contract documents.View AnswerAnswer: D

April 22, 2025 No Comments READ MORE +

Which of the following is NOT required when performing weekly or monthly schedule updates?

Which of the following is NOT required when performing weekly or monthly schedule updates?A . Percent complete.B . Remaining duration of activities.C . Actual finish of activities.D . Original duration of activities.View AnswerAnswer: D

April 18, 2025 No Comments READ MORE +

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):A . The delay must affect the critical path.B . The delay must be concurrent with the delay attributable to both parties.C . The delay must not...

April 18, 2025 No Comments READ MORE +