Which of the following will always describe the critical path? The path with
Which of the following will always describe the critical path? The path withA . The longest duration through the network.B . Zero float.C . Negative float.D . The shortest duration and negative float.View AnswerAnswer: B
A driving relationship is _____________________.
A driving relationship is _____________________.A . A critical relationship.B . A finish-to-start relationship.C . The link between two related activities.D . The link between a predecessor and the activity whose dates it controls.View AnswerAnswer: D
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?A . Use the progressed portion of the critical path of all the updates previous to the current update.B . Use...
Which of the following is NOT a tool or technique used to perform scope planning?
Which of the following is NOT a tool or technique used to perform scope planning?A . Benefit cost analysis.B . Schedule performance indexing.C . Expert Judgment.D . Alternatives identification.View AnswerAnswer: B
What is a key first step in developing a critical path method schedule?
What is a key first step in developing a critical path method schedule?A . Drawing a bar chart of the key phrases of the work.B . Defining the execution plan to meet the required scope of work.C . Setting out the resource to be used and its limitations.D . Drawing...
At a minimum, periodic reporting must be done at what interval?
At a minimum, periodic reporting must be done at what interval?A . Monthly.B . As requested by the project manager.C . As requested by the owner.D . As specified in the contract documents.View AnswerAnswer: D
Which of the following is NOT required when performing weekly or monthly schedule updates?
Which of the following is NOT required when performing weekly or monthly schedule updates?A . Percent complete.B . Remaining duration of activities.C . Actual finish of activities.D . Original duration of activities.View AnswerAnswer: D
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):A . The delay must affect the critical path.B . The delay must be concurrent with the delay attributable to both parties.C . The delay must not...
What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the...
Free float is the
Free float is theA . Difference between the early dates and late dates of an activity.B . Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.C . Difference between the early finish dates and late finish dates of...