Exam4Training

SAP C_TS422_2022 SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing Online Training

Question #1

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

  • A . Create an object selection variant for priority-category-related alerts.
  • B . Assign the alert profile to the overall profile.
  • C . Create an object selection variant for production-planning-related alerts.
  • D . Assign the overall profile to the authorization profile.

Reveal Solution Hide Solution

Correct Answer: B, C
Question #2

where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 Correct answers to this question.

  • A . in the bill of material (BOM)
  • B . in the work centers
  • C . in the MRP controller
  • D . In the routing
  • E . in the production version

Reveal Solution Hide Solution

Correct Answer: A, C, D
Question #3

You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past.

How can you parameterize this in the strategy profile?

  • A . Specify a negative planning horizon.
  • B . Specify a positive planning horizon.
  • C . Specify a positive offset time.
  • D . Specify a negative offset time.

Reveal Solution Hide Solution

Correct Answer: D
Question #4

What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 Correct answers to this question?

  • A . To determine the work in progress along the production line
  • B . To provide timely updates of inventory management for the staged components
  • C . To reduce the total production lead time for a long production line
  • D . To stage different components for a production line simultaneously

Reveal Solution Hide Solution

Correct Answer: A, B
Question #5

Generic Parent » Generic 1 pt

What is the purpose of collective orders?

  • A . To manage production orders for an entire finished product on multiple levels
  • B . To combine order management of co-products and by-products with the main product
  • C . To post production costs on a cost collector instead of the production order
  • D . To post any component withdrawal as single backflush with order confirmation

Reveal Solution Hide Solution

Correct Answer: A
Question #6

You want to schedule an operation finitely, without removing other operations.

Which scheduling strategy do you select?

  • A . Insert operation
  • B . Squeeze in
  • C . Schedule in working time only
  • D . Find Slot

Reveal Solution Hide Solution

Correct Answer: D
Question #7

When you create a sales order

When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?

  • A . When MRP creates a dependent requirement
  • B . When MRP creates a planned order
  • C . When you create a sales order
  • D . When MRP creates a planned order

Reveal Solution Hide Solution

Correct Answer: C
Question #8

What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

  • A . The planned order is converted to a production order.
  • B . The planned order’s component availability is checked.
  • C . The planned order generates capacity requirements
  • D . The planned order’s components are copied to the picking list.

Reveal Solution Hide Solution

Correct Answer: C
Question #9

During production order creation, several valid production versions are found.

How does the system choose the production version?

  • A . Lot size or material cost
  • B . Validity period or sales order
  • C . Planned order or material number
  • D . Alphanumeric or quota arrangement

Reveal Solution Hide Solution

Correct Answer: D
Question #10

What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A . Installation point
  • B . Item type
  • C . Quantity
  • D . Scrap percentage

Reveal Solution Hide Solution

Correct Answer: A, C

Question #11

Your production planners must execute planning only for specific resources.

How can you achieve this in Advanced Planning (PP/DS)?

  • A . Use a propagation range.
  • B . Use a resource group
  • C . Use a planning area.
  • D . Use a planning group.

Reveal Solution Hide Solution

Correct Answer: C
Question #12

in your Plant, MRP is activated.

which options do you have to exclude a material from the MRP run? Note: there are 2 correct answers to this question.

  • A . Use a specific material status
  • B . Use a specific material group
  • C . Use a specific MRP type
  • D . Use a specific MRP list

Reveal Solution Hide Solution

Correct Answer: C, D
Question #13

How can you support a GMP (Good Manufacturing Practice)-compliant production process? Note: There are 3 correct answers to this question.

  • A . Approved resources
  • B . Digital signature
  • C . Batch record
  • D . GMP-compliant flag
  • E . Recipe approval

Reveal Solution Hide Solution

Correct Answer: B, C, E
Question #13

How can you support a GMP (Good Manufacturing Practice)-compliant production process? Note: There are 3 correct answers to this question.

  • A . Approved resources
  • B . Digital signature
  • C . Batch record
  • D . GMP-compliant flag
  • E . Recipe approval

Reveal Solution Hide Solution

Correct Answer: B, C, E
Question #15

Your project uses process orders for the production of liquid chemicals.

What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.

  • A . Resource matrix
  • B . Resource network
  • C . Resource hierarchy
  • D . Resource selection

Reveal Solution Hide Solution

Correct Answer: B, C
Question #16

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,

  • A . By Plant
  • B . By Period
  • C . By Industry
  • D . By Material Status

Reveal Solution Hide Solution

Correct Answer: A, B
Question #17

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

  • A . To increase the number of planning levels
  • B . To simplify the structure of bills of material
  • C . To reduce the number of material masters
  • D . To make the assignment of components easier
  • E . To reduce the number of changes required in bills of material

Reveal Solution Hide Solution

Correct Answer: B, D, E
Question #18

Which of the following questions do you have to answer before you start creating a bill of material (BOM)?

  • A . Is the material type allowed in the BOM?
  • B . Which base unit of measure does the material have?
  • C . What status does the BOM have?
  • D . In which storage location is the BOM required?

Reveal Solution Hide Solution

Correct Answer: A, B
Question #19

Advanced Planning uses master data and transaction data from SAP S/4HANA.

In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.

  • A . Work Center
  • B . Production Version
  • C . Material
  • D . plant

Reveal Solution Hide Solution

Correct Answer: A, C
Question #20

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

  • A . Queue
  • B . Teardown time
  • C . Move time
  • D . Setup Time

Reveal Solution Hide Solution

Correct Answer: A, C

Question #21

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

  • A . setup time
  • B . Opening Period
  • C . Float after Production
  • D . Total replenishment lead time

Reveal Solution Hide Solution

Correct Answer: B, C
Question #22

For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis.

Which of the following do you have to consider? Note: There are 2 correct answers to this question.

  • A . In pro duct-related COC, all costs are debited and credited to a product cost collector.
  • B . Order-related COC is beneficial in a flexible production environment
  • C . Product-related COC is used in manufacturing for co-products
  • D . In order-related COC, individual production orders do NOT have cost segments.

Reveal Solution Hide Solution

Correct Answer: A, B
Question #23

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received.

Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

  • A . Planning with final assembly (40)
  • B . Production by lot size (30)
  • C . Planning at assembly level (70)
  • D . Make-to-order production (20)

Reveal Solution Hide Solution

Correct Answer: B
Question #24

Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA. Note: there are 2 correct answers to this question.

  • A . Manual maintenance
  • B . 100% check
  • C . First in First out (FIFO).
  • D . Simultaneous

Reveal Solution Hide Solution

Correct Answer: A, B
Question #25

Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.

  • A . Changing the storage bin in warehouse management
  • B . Changing the procurement type in the product master
  • C . Changing the operation times in the production data structure
  • D . Changing the stock in inventory management
  • E . Changing the purchasing contract in materials management

Reveal Solution Hide Solution

Correct Answer: B, C, D
Question #26

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

  • A . Order type
  • B . Planning strategy
  • C . Requirements profile
  • D . Requirements type

Reveal Solution Hide Solution

Correct Answer: B, C
Question #27

If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

  • A . Fill up to the maximum stock level.
  • B . Fill up to the safety stock level.
  • C . Fill up based on the lot size procedure.
  • D . Fill up to the reorder stock level.

Reveal Solution Hide Solution

Correct Answer: C
Question #28

Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

  • A . Routing
  • B . Work Center
  • C . Bill of material (BOM)
  • D . Material Master

Reveal Solution Hide Solution

Correct Answer: A, B
Question #29

What are the options if the Dispatched operation status is set for a production order operation? Note: There are 2 correct answers to this question.

  • A . You can reschedule the operation using finite scheduling in a planning table.
  • B . You can reschedule the operation in the Manage Production Operations app.
  • C . You can reschedule the operation using infinite scheduling in a planning table
  • D . You can reschedule the operation using midpoint scheduling in a planning table.

Reveal Solution Hide Solution

Correct Answer: A, B
Question #30

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

  • A . Move Time
  • B . Pick/pack time
  • C . Setup time
  • D . Float before production
  • E . Queue time

Reveal Solution Hide Solution

Correct Answer: B, C, E
Exit mobile version