Question #1

CORRECT TEXT

The system assigns an active inspection type during inspection lot creation.

Where can the system choose the inspection type? Note: 3 correct answer

  • A . From the material specification
  • B . From the Preferred inspection type in material master
  • C . From the Quality level
  • D . From the Quality info Record
  • E . From the inspection type assigned to an order type

Reveal Solution Hide Solution

Correct Answer: B, C, E
Question #2

During the production inspection, which elements does the system use to determine the layout of results and defects recordings? Note: 3 correct answer

  • A . Report type
  • B . Confirmation profiles
  • C . Code groups
  • D . Partner profiles
  • E . Status profiles

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #3

Your customer plan to use Test Equipment Management as part of QM.

What event triggers the creation of an inspection lot for calibration inspection?

  • A . Scheduling a maintenance plan
  • B . Assignment of Equipment to a maintenance plan
  • C . Creation of maintenance order
  • D . Release of a maintenance order

Reveal Solution Hide Solution

Correct Answer: D
Question #4

What is the difference audit between audit question and corrective preventive action? Correct 2

  • A . Corrective actions have partners
  • B . Audit questions have no status
  • C . Audit question have no long texts
  • D . Corrective actions have no search field

Reveal Solution Hide Solution

Correct Answer: A,B
Question #5

Your customer automatically create inspection lot for general deliveries in sales and distribution process for its production.

If QM not started result recording what does the system do in response to a change in the material quality……………..

  • A . Change the quality of the current inspection lot
  • B . Block the current inspection lot from processing
  • C . Cancel the current inspection lot and create a new one
  • D . Create a new inspection lot with the different quantity

Reveal Solution Hide Solution

Correct Answer: A
Question #6

Your customer user action boxes in the notification processing and wants relationships to exist between the different.

In which implementation guide activity do you define these relationships?

  • A . Activity catalog
  • B . Customer status scheme
  • C . Functions for action box
  • D . Task catalog

Reveal Solution Hide Solution

Correct Answer: C
Question #7

Your customer wants to periodically calibrate the quality management test equipment used in an inspection plan.

Which type of test equipment must used?

  • A . Production resource/ tools PRTs
  • B . Documents
  • C . Equipment
  • D . Materials

Reveal Solution Hide Solution

Correct Answer: C
Question #8

During which of the following steps in a business process does a dynamic modification rule change severely.

  • A . The creation of a inspection Lot
  • B . The creation of a certification
  • C . Creation of a batch
  • D . The creation of a notification

Reveal Solution Hide Solution

Correct Answer: A
Question #9

You can assign combination of material number and plants to one inspection plan.

Which organization structure must the plants share for correct cost collection in the inspection handlings?

  • A . Sales organization
  • B . Purchase organization
  • C . Company code
  • D . Controlling Area

Reveal Solution Hide Solution

Correct Answer: D
Question #10

You can user business application programing interface (BAPIs) for different tests.

Which of the following statements describes a BAPI?

  • A . An enhancement point
  • B . A reporting transaction
  • C . A customer exit
  • D . Complex function module

Reveal Solution Hide Solution

Correct Answer: D

Question #11

Which business object must you use to create a stability study?

  • A . Sample drawing procedure
  • B . Quality notification
  • C . Quality inspection lot
  • D . Physical sample

Reveal Solution Hide Solution

Correct Answer: B
Question #12

Your customer uses MIC and requests automatic defect recording After configuration defect recording the implementation Guide, which additional steps must you perform to satisfy customer requirements? (2 correct ans)

  • A . Activate defects recording in the characteristic control indicator for your MIC
  • B . Assign an inspection method to your MIC
  • C . Assign a notification type to an inspection type
  • D . Select the radio button to activate quality notification in the defect class

Reveal Solution Hide Solution

Correct Answer: A,C
Question #13

Which of the following QM business processes can require a user’s digital signature? (3 Correct Ans)

  • A . Approval of quality notification
  • B . Result recording in the inspection Lot
  • C . Defective recording in the inspection Lot
  • D . Manual confirmation of a physical sample drawing
  • E . UD for an inspection lot

Reveal Solution Hide Solution

Correct Answer: B,D,E
Question #14

Which Status allows you to make a usage decision without using the force inspection competition function for all mandatory characteristic results?

  • A . 5
  • B . 6
  • C . 2
  • D . 1

Reveal Solution Hide Solution

Correct Answer: A
Question #15

During an inspection the lab technicians record the same test values for an inspection characteristic.

Which of the following do they assign to the products?

  • A . As a partial lot
  • B . As a batch
  • C . As an inspection point
  • D . As a sample size

Reveal Solution Hide Solution

Correct Answer: C
Question #16

What type of task lists can the calibration planner assign to a maintenance plan to perform a calibration inspection? Note: 2 correct answer

  • A . General task list
  • B . Standard routing
  • C . Equipment task list
  • D . Inspection plan
  • E . Functional location task list

Reveal Solution Hide Solution

Correct Answer: A,C
Question #17

The IMG includes a customizing activity in which you assign object categories to a notification type?.

Which of the following object category already exist in standard setting? (3 Correct Ans)

  • A . Serial number
  • B . Batch
  • C . Purchase order item
  • D . Material
  • E . Order(pp-pi)

Reveal Solution Hide Solution

Correct Answer: A,B,D
Question #18

You want to print a certificate for an outbound delivery, at which level is a certificate printed?

  • A . Delivery Item level
  • B . Delivery header level
  • C . Shipping point level
  • D . Material level

Reveal Solution Hide Solution

Correct Answer: A
Question #19

Your customer wants to automatically valuate the overall results of an audit using the standard.

Which valuation method book scores for the overall result? (2 Correct ans)

  • A . Valuation mode
  • B . Quantitative valuation
  • C . Qualitative valuation
  • D . Non relevant indicator

Reveal Solution Hide Solution

Correct Answer: B,C
Question #20

A buyer creates a purchase order for a material for which QM in procurement is active

What does the system verify when a target QM system is assigned to the material master? Note: 3 Correct answer

  • A . The defined assignments for QM systems in the implementation Guide (IMG)
  • B . The vendor master
  • C . The inspection type
  • D . The QM quality info record
  • E . The purchasing info record

Reveal Solution Hide Solution

Correct Answer: A,B,D

Question #21

A buyer wants to quality management department to approve a new vender malarial – combination.

After activating the QM in procurement process, what the quality management department ensure in……Correct 2

  • A . The material master has an active inspection type
  • B . A valid release quality info record exists
  • C . The inspection plan includes a relevant control key at operation level
  • D . The material master has a relevant QM Control key assigned to it
  • E . A quality agreement for vendor master exists

Reveal Solution Hide Solution

Correct Answer: B,E
Question #22

Your customer record defects a characteristic level with in result recording and wants to correct all defects for each inspection.

How do you satisfy the customer requirement?

  • A . In the implementation guide IMG select the active quality notification checkbox in the defect class for…..
  • B . Use the same report type for all inspection operations
  • C . Active defect recoding in the control indicators of the characteristics used in the inspection plan
  • D . In the implementation guide, select the one Q-Notification per inspection type

Reveal Solution Hide Solution

Correct Answer: C
Question #23

Which QM master data must you maintain to separate a sample into a primary and reserve sample?

  • A . Sample determination
  • B . Sample drawing procedure
  • C . Sample processes
  • D . Sample size

Reveal Solution Hide Solution

Correct Answer: B
Question #24

Your customer wants material -dependent code selected from a catalog to show when a Where can you control and limit the codes?

  • A . Catalog profile
  • B . Catalog settings
  • C . Catalog groups
  • D . Product hierarchy

Reveal Solution Hide Solution

Correct Answer: A
Question #25

Which settings are required for the immediate creation of inspection instruction during goods receipt process. Note: 3 correct answer

  • A . Control setting in quality info record
  • B . Inspection type settings in the implementation guide (IMG)
  • C . Settings for print control in implementation Guide (IMG)
  • D . Control setting in characteristic of the task list
  • E . Inspection type settings in Material master

Reveal Solution Hide Solution

Correct Answer: B,C,D
Question #26

Which following inspection origin are directly related to sale and distribution (SD) functions 3 correct answers

  • A . Goods issue
  • B . General delivery
  • C . Delivery to customer with customer order
  • D . Good receipts
  • E . Plant maintenance

Reveal Solution Hide Solution

Correct Answer: B,C,D
Question #27

In the material master, at which organizational level do you create Quality management (QM) data for inspection type.

  • A . Company code level
  • B . Plant level
  • C . Business area level
  • D . Client level

Reveal Solution Hide Solution

Correct Answer: B
Question #28

When creating an operation step in an inspection plan, which of the following is mandatory?

  • A . Work center
  • B . Activity type
  • C . Control key
  • D . Standard text

Reveal Solution Hide Solution

Correct Answer: C
Question #29

During an in process inspection for production orders, such as inspection type 09, which inventory posting is possible?

  • A . Blocked stock
  • B . Unrestricted Stock
  • C . Quality stock
  • D . None

Reveal Solution Hide Solution

Correct Answer: D
Question #30

Your customer wants to add the quality score of a material as criterion for the vendor evaluation.

Where do you set the calculation procedure for the quality score?

  • A . Quality info record in procurement
  • B . Vendor master
  • C . Material master
  • D . UD code

Reveal Solution Hide Solution

Correct Answer: D