Per best practices, a Create Assets Auto Task should occur at what point during an Orchestration Plan?

Per best practices, a Create Assets Auto Task should occur at what point during an Orchestration Plan?
A . As the last orchestration item
B. Once order processing has begun, it makes no difference when assets are created.
C. After the fulfillment request callout has reached a completed state
D. As the second-to-last orchestration item

Answer: D