Once the migrate completes, to which size should you set the ExpressRoute circuit to the New York office to meet the business goals and technical requirements?

Once the migrate completes, to which size should you set the ExpressRoute circuit to the New York office to meet the business goals and technical requirements?
A . 500 Mbps
B . 1,000 Mbps
C . 2,000 Mbps
D . 5,000 Mbps

Answer: C

Explanation:

ExpressRoute circuits are configured to allow you to burst up to two times the bandwidth limit you procured for no additional cost.

Scenario: It is estimated that during the migration, the bandwidth required between Azure and the New York office will be 1 Gbps. After the migration, a traffic burst of up to 3 Gbps will occur.

References: https://docs.microsoft.com/en-us/azure/expressroute/expressroute-faqs

Latest AZ-120 Dumps Valid Version with 125 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments