In which scenario should you set redundancy for master modules to be highly available?

You are creating a Logical Interconnect Group for a three-frame HPE Synergy solution with HPE Virtual Connect SE100Gb F32 Modules for Synergy.

In which scenario should you set redundancy for master modules to be highly available?
A . When storm control or loop protection will be enabled for Virtual Connect modules
B . When each of the frames has two Virtual Connect modules installed
C . When each Virtual Connect module is installed in different frame
D . When each Virtual Connect module is installed in different fabric

Answer: A

Latest HPE2-T37 Dumps Valid Version with 40 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments