In which of the steps of NIST’s risk assessment methodology are the boundary of the IT system, along with the resources and the information that constitute the system identified?

In which of the steps of NIST’s risk assessment methodology are the boundary of the IT system, along with the resources and the information that constitute the system identified?
A . Likelihood Determination
B . Control recommendation
C . System characterization
D . Control analysis

Answer: C