In which of the following cases, would an organization be more prone to risk acceptance vs. risk mitigation?
In which of the following cases, would an organization be more prone to risk acceptance vs. risk mitigation?
A . The organization uses exclusively a quantitative process to measure risk
B. The organization uses exclusively a qualitative process to measure risk
C. The organization’s risk tolerance is high
D. The organization’s risk tolerance is lo
Answer: C