In this scenario, which statement is correct?

Refer to the exhibit.

A volume move operation has been initiated to move a volume named Mirrsrc from one aggregate to another. The operation failed with the error that is shown in the exhibit.

In this scenario, which statement is correct?
A . Manually trigger the cutover process in order to restart the job.
B . The volume move cannot be completed at this time because of high use on the node.
C . There are too many snapshots on the source volume.
D . Cancel and restart the volume move operation.

Answer: C