In this scenario, the organization agreed to which of the following types of contracts?
A organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000.
In this scenario, the organization agreed to which of the following types of contracts?
A . A cost-reimbursable contract.
B. A lump-sum contract.
C. A time and material contract.
D. A bilateral contract.
Answer: B
Latest IIA-CIA-Part3 Dumps Valid Version with 402 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	