In the scrum lifecycle of a project, when should the team agree on the requirements for the Definition of Done?

In the scrum lifecycle of a project, when should the team agree on the requirements for the Definition of Done?
A . Before getting started on the project
B . During the sprint retrospective
C . During the backlog refinement
D . After the sprint planning

Answer: A

Explanation:

Before getting started, teams need to make important decisions about how the extended team will work together during the project. These include: Scheduling the key ceremonies on a fixed cadence including: daily scrum, sprint planning, sprint review, backlog refinement, sprint review and the sprint retrospective. Design the development workflow and configure the project management tool (e.g. Jira). Define the deployment pipeline and configuration management process. Agree the Definition of Done (DoD) and Definition of Ready (DoR).

Latest ACD100 Dumps Valid Version with 56 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments