In a rolling forecast table, what can be used to determine the date to cut over to plan data?

In a rolling forecast table, what can be used to determine the date to cut over to plan data?
A . Look back x number of months
B . Last actual value
C . Look ahead x number of months
D . Current date with an offset

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments