If an activity time within a critical path is increased, which of the following is most likely to occur?

If an activity time within a critical path is increased, which of the following is most likely to occur?
A . The project will be delayed.
B . Additional resources will have to made available.
C . Costs will increase.
D . All activities in the project will be affected.

Answer: A