How should a Development Team deal with non-functional requirements?
How should a Development Team deal with non-functional requirements?
A . Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.
B . Assign them to the lead developers on the team.
C . Handle them during the Integration Sprint preceding the Release Sprint.
D . Ensure every Increment meets them.
Answer: D