How many jobs go Active when the job is started, excluding parent jobs?

An administrator has a backup policy with the following attributes:

Allow multiple data streams is selected

Max Jobs per Client value set to 4

How many jobs go Active when the job is started, excluding parent jobs?
A . 8
B. 9
C. 12
D. 15

Answer: C