For which objects can you revaluate activities and business processes at actual prices? There are THREE correct answers for this question

For which objects can you revaluate activities and business processes at actual prices? There are THREE correct answers for this question
A . Work breakdown structure elements
B . Cost centers
C . Profit centers
D . Work centers
E . Profitability segments

Answer: A,C,E