A project’s installation start involves a Kickoff Meeting and the General Contractor’s Coordination Meeting. As part of the designer’s responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
- A . Project submittal approval process
- B . RFI process
- C . Payment procedures
- D . Punch List process
- E . Project start and completion dates
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
- A . 8
- B . 16
- C . 32
- D . 64
What is the RECOMMENDED bend radius of a conduit with an internal diameter of 51 mm (2 in)?
- A . 203 mm (8 in)
- B . 305 mm (12 in)
- C . 406 mm (16 in)
- D . 508 mm (20 in)
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly.
Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)
- A . Lower dB loss values
- B . Stretching of copper conductors and breakage of optical fiber strands
- C . Increased Interference levels
- D . Reduced expected useful life and performance
- E . Slippage between the cable core and the sheath
The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter What increase in usable floor space should another 103 mm (four trade size) sleeve be added?
- A . =929 m2 (10,001 ft2)
- B . =1858m2 (20,001 ft2)
- C . =3716 m2 (40,001 ft2)
- D . =4645 m2 (50,001 ft2)
An ICT distribution designer is reviewing a client’s site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process
- A . logical network
- B . top-down
- C . bottom-up
- D . functional
Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
- A . Authority
- B . Having Jurisdiction (AHJ)
- C . Construction Manager
- D . ICT Distribution Designer/Project Manager
The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system.
What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?
- A . 2
- B . 4
- C . 6
- D . 8
Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)
- A . Proximity to interfering sources
- B . Missing or inadequate optical connections
- C . Missing or inadequate device or cable shielding
- D . Interface designs
- E . Input signal lines
What step can be a phase of the Bidding and Negotiating process?
- A . Prepare necessary change orders
- B . Identifying any conflicts that may become apparent
- C . Creating a response evaluation
- D . Identifying potential value engineering opportunities