Based on the chart above, what is the most appropriate next test phase?

Given is the following defect removal chart reported at the end of system testing – showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.

Based on the chart above, what is the most appropriate next test phase? 1 credit
A . Acceptance testing to verify the business process
B . Acceptance testing to verify operational requirements
C . Requirements testing as part of testing regulatory compliance
D . Another system test cycle to verify defect resolution

Answer: D