Based on "Sprint 7 Burndown Chart" would you do anything different in Sprint 8?

Based on "Sprint 7 Burndown Chart" would you do anything different in Sprint 8?

A . Stakeholders will encourage the Scrum Team to estimate better during the Sprint 8 Planning Meeting.
B. There is nothing wrong The Developers will present all Product Backlog Items selected for Sprint 7 at the end of the Sprint.
C. The Product Owner may ask the Developers to complete the unfinished Product Backlog Items from Sprint 7 in Sprint 8.
D. The Scrum Master adds additional Developers for Sprint 8.
E. The Developers may forecast less overall work in Sprint 8.
F. The Developers put incomplete Product Backlog Items back into the Product Backlog for re-ordering.
G. The Developers carry over incomplete Sprint Backlog items from Sprint 7 to Sprint 8 and monitor the Sprint 8 burn-down chart. As soon as deviation from trends is detected the Developers work with the
Product Owner to negotiate remaining work.

Answer: E,F