What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?

What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
A . Foundation Summary
B. Delivery Plan
C. Terms of Reference
D. Management Approach Definition

Answer: D

Which statement applies to the DSDM process?

Which statement applies to the DSDM process?
A . Can be configured and calibrated to cater for light or strong governance
B. DSDM projects can deliver the phases in the DSDM process in any order
C. Does not require the elaboration of supporting products for complex projects
D. Provides an approach that can be used for all projects without change

Answer: A