In which of the following situations does a review of the internal interval need not be conducted?

The internal inspection interval must be reviewed whenever changes occur that could affect the degradation of the vessel. In which of the following situations does a review of the internal interval need not be conducted?A . operating temperature increasesB . operating pressure decreasesC . operating pressure increasesD . fluid composition...

March 13, 2024 No Comments READ MORE +

Pneumatic testing may be substituted for hydrostatic testing provided all but which of the following?

Pneumatic testing may be substituted for hydrostatic testing provided all but which of the following?A . Water is not readily availableB . RefractoryC . TemperatureD . ProcessView AnswerAnswer: A

March 13, 2024 No Comments READ MORE +

Increasing hardness of the metal substrate is not always a good indicator of improved resistance to __________, particularly where corrosion plays a significant role.

Increasing hardness of the metal substrate is not always a good indicator of improved resistance to __________, particularly where corrosion plays a significant role.A . stress corrosionB . erosionC . stress corrosion crackingD . ductile failureView AnswerAnswer: B

March 12, 2024 No Comments READ MORE +

When discussing repairs to a pressure vessel what is the definition of 'construction codes'?

When discussing repairs to a pressure vessel what is the definition of 'construction codes'?A . The NBICB . The current ASME Code editionC . The API 510 CodeD . The Code the vessel was constructed to including non-standard and jurisdictional special vesselsView AnswerAnswer: D

March 12, 2024 No Comments READ MORE +

Which of the following relief devices is intended to work with steam boilers?

Which of the following relief devices is intended to work with steam boilers?A . Relief Valve.B . Safety Relief Valve.C . Safety Valve.D . Balanced Safety Relief.View AnswerAnswer: C

March 12, 2024 No Comments READ MORE +

When a crack is discovered in a vessel that is in a highly stressed area, what action should you recommend to be considered as a first step in any effort to correct the flaw?

When a crack is discovered in a vessel that is in a highly stressed area, what action should you recommend to be considered as a first step in any effort to correct the flaw?A . Call in a pressure vessel engineerB . Design an overlay patch to completely cover the...

March 10, 2024 No Comments READ MORE +

After a vessel has been placed in service, what Code is used to evaluate?

After a vessel has been placed in service, what Code is used to evaluate?A . ASME Section VIIIB . ASME Section VC . API 572D . API 510View AnswerAnswer: D

March 10, 2024 No Comments READ MORE +

The definition of pressure vessels is:

The definition of pressure vessels is:A . A container designed to withstand internal or external pressureB . A vessel for the containment of process fluids with or without internal pressureC . A container designed to operate below atmospheric pressureD . A container no greater than 8” in cross sectionView AnswerAnswer:...

March 10, 2024 No Comments READ MORE +

Which is the most severe stress caused by internal pressure in a cylindrical shell?

Which is the most severe stress caused by internal pressure in a cylindrical shell?A . Longitudinal stress acting along the longitudinal axisB . Circumferential stress acting along the longitudinal axisC . Circumferential stress acting along the circumferential axisD . Longitudinal stress acting along the circumferential axisView AnswerAnswer: B

March 9, 2024 No Comments READ MORE +

An on-stream inspection can NOT be substituted for an internal inspection unless the remaining life exceeds:

An on-stream inspection can NOT be substituted for an internal inspection unless the remaining life exceeds:A . 2 yearsB . 4 yearsC . 5 yearsD . 10 yearsView AnswerAnswer: D

March 9, 2024 No Comments READ MORE +