After there is an approved labor change to a project, what should the project manager do NEXT?
After there is an approved labor change to a project, what should the project manager do NEXT?
A . update the schedule
B . order the equipment
C . issue an invoice for the change
D . inform the purchasing department
Answer: A
Explanation:
Once a labor change is approved, the next step for the project manager is to update the project schedule. Changes in labor can affect the timeline of the project, and updating the schedule ensures that all stakeholders are aware of the new timelines and can adjust their plans accordingly. This step is critical for maintaining project organization and ensuring that the project stays on track despite the changes.