After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.

After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.

This is an example of
A . Risk Tolerance
B . Qualitative risk analysis
C . Risk Appetite
D . Quantitative risk analysis

Answer: D