Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
A . Use gross building square footages. The pluses and minuses all average out.
B . Look at each activity independently and don’t follow specific logic paths when assigning activity durations.
C . Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
D . Use the people responsible for performing the work as a resource to assign activity durations.
Answer: D