According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?
Refer to the exhibit.
According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?
A . Week 3
B . Week 4
C . Activity B
D . Milestone X
Answer: D
Explanation:
In the provided Gantt chart, Activity C is scheduled to start after the completion of Milestone X. This is evident as the milestone symbol (diamond) for Milestone X appears right before the beginning of Activity C, indicating that Activity C is dependent on the completion of Milestone X.