A service provider wants to deploy a change that will affect the end-to-end service. Who is responsible for confirming that the change has been evaluated for risk?

A service provider wants to deploy a change that will affect the end-to-end service. Who is responsible for confirming that the change has been evaluated for risk?
A . change management forum
B . integrated change advisory board
C . service owner
D . service provider

Answer: B

Latest SIAMF Dumps Valid Version with 40 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments