A report scheduled to run every 15 mins. but takes 17 mins. to complete is in danger of being_____.

A report scheduled to run every 15 mins. but takes 17 mins. to complete is in danger of being_____.
A . skipped or deferred
B . automatically accelerated
C . deleted
D . all of the above

Answer: A

Explanation:

A report that is scheduled to run every 15 minutes but takes 17 minutes to complete is in danger of being skipped or deferred2. This means that Splunk may skip some scheduled runs of the report if they overlap with previous runs that are still in progress or defer them until the previous runs are finished2. This can affect the accuracy and timeliness of the report results and notifications2. Therefore, option A is correct, while options B, C and D are incorrect because they are not consequences of a report taking longer than its schedule interval.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments