What should you do?
A company uses the built-in master planning engine but plans to use Planning Optimization instead. You enable auto-firming. You need to ensure that planned orders are firmed within the current month .
What should you do?
A . Set the firming time fence to one month plus issue margin.
B . Set the firming time fence to one month plus receipt margin
C . Set the firming time fence to one month plus lead lime rf the lead time is greater than one week.
D . Set the firming time fence to one month
E . Set the firming time fence to one week plus lead time if the lead time is less than one week.
Answer: D