Which switch configuration can meet these requirements?
A customer is planning to deploy a branch office server rack.
The environment will have the following requirements:
– Single rack with 20 HPE ProLiant DL360 Gen10 Servers.
– Each Server will have 6 x 10G SFP+ Ports.
– Each Server will have a dedicated iLO port.
– The customer requires that only two switches be used.
– The customer requires separate control planes.
Which switch configuration can meet these requirements?
A . 2 × HPE 5945 Series switch with IRF
B . 2 × Aruba 8325 Series switches with VSX
C . 2 × HPE 5945 Series switches standalone
D . 2 × Aruba 8325 Series switches with backplane stacking.
Answer: C