Given the cashflows below, which of the following is correct?
Given the cashflows below, which of the following is correct?

A . The project pays back in year 4 of the project.
B . The project does not pay back within the four year period.
C . The project pays back in year 2 of the project.
D . The project pays back in year 3 of the project.
Answer: B