Which of the following is NOT required when initially planning a project?

Which of the following is NOT required when initially planning a project?
A . Resource Identification and leveling.
B . The duration of each task.
C . A schedule that identifies tasks required on a project.
D . Logical relationships between the tasks.

Answer: A