Mira is working on a story. All of a sudden, the links to all three bugs related to the story disappeared. All issues including the story and the three bugs are tracked in the DEV project, which is a classic Software project.

Mira is working on a story. All of a sudden, the links to all three bugs related to the story disappeared. All issues including the story and the three bugs are tracked in the DEV project, which is a classic Software project.

Which four can explain the situation (Choose four)
A . Issue linking was disabled globally
B . Link issues permission was revoked for Mira
C . The links to the bugs were deleted
D . The linked bugs were deleted
E . Browse Projects permission was revoked for Mira
F . A security level was applied to the linked bugs

Answer: A, B, C, D