After an Agile Release Train’s first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?

After an Agile Release Train’s first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?
A . Ask Product Management and the System Architect what the new Program Back-log looks like just before the next Innovation and Planning (IP) Iteration, so social-ization can begin
B . Compile all the teams’ objectives from PI Planning and send out a summary report
C . Coach Product Management and the System Architect to include Program Backlog refinement into their cadence-based approach
D . Ask the Lean Portfolio Management function to hold regular Epic review meetings so new Epics will flow to the Agile Release Train

Answer: C