What should the project manager do?
While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers.
What should the project manager do?
A . Discuss this with the functional manager and related parties.
B. Reject the functional manager’s change request immediately.
C. Analyze the impact of the change request on the project.
D. Apply for a formal change control board (CCB) approval.
Answer: C