How should DSDM team measure progress?
How should DSDM team measure progress?
A . Through a project dashboard
B. Based on what has been delivered at the end of a Timebox.
C. Based on the completion of activities rather than the delivery of products
D. Through an analysis of the Instrumental Success Factors.
Answer: B