Which solution meets these requirements?

A company data center requires a new disaster recovery solution to host critical services. The solution can sustain several hours of data loss because the services are routinely backed up to an offsite location. Also, the disaster recovery solution must provide 24-hour availability. Due to the strict policy requirements, the company wants to retain complete control of when the failover process occurs.

Which solution meets these requirements?
A . active/active
B. hot standby
C. warm standby
D. cold standby

Answer: D