Programmatic objective Milestones include all the following except: (Choose three)
Programmatic objective Milestones include all the following except: (Choose three)
A . Transparency Metrics
B. Learning Metrics
C. Process Metrics
D. Product Metrics
E. Progress metrics
Answer: C,D,E
Explanation:
https://www.scaledagileframework.com/metrics/