When calculating the cost of delay, which of the following does not reflect the time criticality?
When calculating the cost of delay, which of the following does not reflect the time criticality?
A . What is the revenue impact on our business?
B. Is there a fixed deadline?
C. What is the current effect on customer satisfaction?
D. Will they wait for us or move to another solution?
Answer: A
Explanation:
https://www.scaledagileframework.com/wsjf/