When can Product Backlog Refinement occur?

When can Product Backlog Refinement occur?
A . Anytime during the Sprint.
B. Only during Sprint Planning.
C. Before Sprint Planning.
D. Only during Refinement meetings planned by the Product Owner.

Answer: A