Which of the following would be an appropriate name for a use case that allows a project manager to allocate resources to a project?

Which of the following would be an appropriate name for a use case that allows a project manager to allocate resources to a project?
A . Assign resources
B. Resource.
C. Project Manager
D. Project.

Answer: A