What is the risk with this plan?
Universal Containers is building a new complex integration to a legacy system. the legacy system is also going through a major upgrade. Senior leadership has committed to the board that the combined programs will be completed on time.
What is the risk with this plan?
A . The deadline is scheduled during a Salesforce release
B. The project team has decided to use the Waterfall methodology
C. The legacy system team is using an Agile methodology
D. Multiple work -streams with dependencies could impact the go-live
Answer: D