Which two are valid actions?
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)A . Recruit additional Development Team members before the work can begin.B . The Development Team ensures that the Product Owner is aware, starts the...