You need a graphical view that shows the current schedule to baseline.Which view should you use?

You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates.

You need a graphical view that shows the current schedule to baseline.Which view should you use?
A . Tracking Gantt view
B . Leveling Gantt view
C . Detail Gantt view
D . Gantt Chart view

Answer: A