Why should the outcome of the PMO maturity assessment always be presented in three dimensions?
Why should the outcome of the PMO maturity assessment always be presented in three dimensions?
A . To meet the needs of upper management.
B . To meet the short, medium and long term.
C . Because maturity evolves independently in each of these dimensions (strategic, tactical or operational).
D . To ensure that all necessary functions are being performed by the PMO.
Answer: C
Explanation:
The outcome of the PMO maturity assessment is presented in three dimensions―strategic, tactical, and operational―because maturity in these areas often evolves independently. The PMO may be mature in operational aspects like process execution while still developing its strategic role within the organization. This multidimensional assessment provides a complete view of the PMO’s strengths and areas for improvement, ensuring balanced growth across all critical functions.
Latest PMO-CP Dumps Valid Version with 40 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund