Why is the program predictability measure the primary Metric used during the quantitative measurement part of the Inspect and Adapt event?
A . To measure the predictability of business value delivered in the PI timebox
B . To predict the scope of the remaining requirements in the Program Backlog
C . To forecast when remaining features could be delivered to customers
D . To match customer demand to the Agile Release Train’s velocity
Answer: A
Explanation:
The program predictability measure is the primary metric used during the quantitative measurement part of the Inspect and Adapt (I&A) event in SAFe. This measure assesses how reliably the Agile Release Train (ART) can deliver business value within the Program Increment (PI) timebox. It helps to: Evaluate the team’s ability to meet their commitments. Identify areas where predictability can be improved.
Ensure that the business value planned for the PI is actually delivered.
By focusing on the predictability of business value, organizations can better align their planning and execution efforts, ultimately enhancing customer satisfaction and achieving strategic goals more effectively.
SAFe Scrum Master Reference
SAFe Inspect and Adapt events
SAFe 5.0 framework: using program predictability as a key metric to assess and improve ART performance.