Which type of document should the BA create to achieve the objective?

The business analyst (BA) at Universal Containers is responsible for defining the enhancement features for the current Salesforce CPQ implementation that must be configured in the next phase of the project.

Which type of document should the BA create to achieve the objective?
A . Business analysis plan
B . Scope statement specification
C . Functional requirements specification

Answer: B

Subscribe
Notify of
guest
1 Comment
Inline Feedbacks
View all comments
Edwin Rodriguez
Edwin Rodriguez
12 days ago

The correct answer is C: Functional requirements specification since the features are the key of functional requirements