Exam4Training

Which test management control option is most appropriate to adopt under these circumstances?

Topic 5, Scenario 4, V2 "Test Management Tool"

The project situation after 11 months is:

– The first increment was released one week late but contained sufficient functionality to be declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.

– The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.

– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).

– Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which test management control option is most appropriate to adopt under these circumstances? 2 credits
A . Introduce mandatory evening and weekend working to retrieve the 3 week slippage.
B . Reconsider the exit criteria and review the test plan in the context of the current situation.
C . Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.
D . Arrange a meeting with the user community representatives to discuss the user interface.

Answer: B

Exit mobile version